ALMM List-II for solar cells: what rooftop and open access buyers need to know

What ALMM List-II means for factories buying rooftop or open access solar — which projects it covers, how to check compliance, and what to ask suppliers.

By ANR Horizon Editorial Team · · 4 min read

Solar panels on a large industrial rooftop at sunset

The Approved List of Models and Manufacturers (ALMM) is India's register of solar equipment approved for use in specified projects. List-I covers modules. List-II covers solar cells, and since 1 June 2026 it has been in force: eligible projects must use List-I modules made with List-II cells.

For a factory or commercial building installing rooftop solar, or buying power through open access, this affects equipment choice, cost and paperwork. This guide explains what to check.

What the requirement says

As reported when List-II came into force:

  • Eligible projects must use modules from ALMM List-I made with cells from ALMM List-II
  • It covers government and government-supported projects, specified procurement arrangements, and net-metering and open access projects commissioned on or after the effective date, subject to exemptions
  • MNRE did not grant a blanket extension, but said it would consider case-by-case relief for projects at an advanced stage
  • A List-III for ingots and wafers is scheduled for June 2028

In October 2026, PV Tech reported a limited exemption for certain net-metering and open access projects until 31 December 2026. Exemptions are specific — check the current MNRE order rather than assuming your project qualifies.

Enlisted capacity is growing

Domestic cell manufacturing has been expanding. MNRE's 12th revision of List-II on 8 October 2026 took total enlisted capacity to about 37.8 GW, according to PV Tech. More enlisted capacity generally means more choice and supply for buyers, though prices and availability vary.

Why it matters for C&I buyers

Cost

Modules made with domestic cells may cost more than modules with imported cells, depending on the market. This affects CAPEX projects directly and OPEX tariffs indirectly. See CAPEX vs OPEX solar for factories.

Availability

Lead times for compliant modules depend on supply. Build procurement time into the schedule.

Compliance risk

A non-compliant system may face problems with net-metering approval or open access eligibility. The risk falls on the project owner unless the contract shifts it.

What to ask your supplier or EPC

  • Which module model and cell model will be used?
  • Are both on the current ALMM lists? Show the revision.
  • What documents will prove compliance — invoices, serial numbers, manufacturer declarations?
  • Who bears the risk if compliance is questioned?
  • Are there substitution rules if the specified module isn't available?

See how to evaluate an EPC contractor.

Put it in the contract

EPC and supply contracts should:

  • Name the module and cell models, or require ALMM-compliant equivalents
  • Require compliance documents at delivery
  • Make the contractor responsible for non-compliance
  • Link payment milestones to compliant delivery

For OPEX/RESCO arrangements, the developer owns the system, but compliance still affects your net-metering connection. Ask how they will document it. See what is a PPA.

Keep records

Keep serial numbers, invoices and compliance documents in your project file. They matter for approvals, inspections, warranty claims and any future sale of the facility. See building a project documentation file and module degradation and warranties.

Open access and group captive supply

If you buy power from an off-site plant, the plant's compliance is the developer's responsibility, but it can affect the project's approvals and timelines. Ask developers how they are meeting ALMM requirements. See open access vs group captive.

How ALMM fits with other requirements

ALMM is one of several requirements that affect equipment choice. Others include quality standards and certifications for modules and inverters, grid-connection requirements of the distribution company, and, for some schemes, domestic content rules. A compliant module must still be the right module for the site — its efficiency, temperature behaviour, mechanical strength and warranty matter as much as its listing. See solar module degradation and warranties and bifacial solar modules explained.

Timing your project

Because exemptions and requirements depend on dates — bid dates, commissioning dates and order effective dates — the project timeline matters. A project planned for commissioning just before or after a cut-off date can fall on either side of a requirement. Build a margin into your schedule, and make sure your EPC contract says what happens if a delay moves the project into a different compliance regime. See where renewable project schedules slip.

A quick buyer checklist

  • Confirm whether your project type is covered and from what date
  • Get module and cell model numbers in writing
  • Check both against the latest ALMM revisions
  • Put compliance and documentation duties in the contract
  • Store serial numbers and certificates in your project file

Common mistakes

  • Assuming your project is exempt without checking the order
  • Accepting "ALMM compliant" without model numbers
  • Not checking cells as well as modules
  • Leaving compliance risk with the buyer by default
  • Losing serial number records after installation

Sources

  • TaiyangNews, "India brings ALMM List-II for solar cells into force", 1 June 2026: taiyangnews.info
  • PV Tech, "India's MNRE issues 12th solar cell ALMM revision, capacity reaches 37.8GW", October 2026: pv-tech.org

How we help

Through C&I solar, open access and group captive and EPC partner coordination, we help buyers write compliance into contracts and check that partners can deliver compliant equipment.